G.I. City Council approves 3 items concerning Good Life District project


Mitch Hohlen, director of development with Woodsonia Real Estate of Elkhorn, talks to the Grand Island City Council Nov. 17 about progress with the Good Life District project. (Carol Bryant, Central Nebraska Today)
Mitch Hohlen, director of development with Woodsonia Real Estate of Elkhorn, talks to the Grand Island City Council Nov. 17 about progress with the Good Life District project. (Carol Bryant, Central Nebraska Today)

GRAND ISLAND – The Grand Island City Council approved three agenda items, each by a 9-0 vote, concerning the Good Life District project.

City Council member Doug Lanfear was absent from the meeting.

Total estimated project costs are $626,594,675, which is labeled as the largest development project in Grand Island’s history.

After the City Council had approved the three agenda items, Mayor Roger Steele commented about moving forward with the Good Life District project and praising the City Council and city staff members for their work.

“This is the largest development project in the history of Grand Island. Nothing else even compares. It provides for a sports complex, a YMCA, an aquatics center, much needed housing and commercial development. I congratulate the City Council for tackling a project of this immense size. This project is huge. This project is monumental,” Steele said. 

“This project will set Grand Island apart for decades to come. I doubt we will take on a project this big for decades to come. That’s how big this is. I congratulate you City Council members,” the mayor said.

“My thanks also go to Patrick Brown and Chad Nabity and several other city employees who spent many hours. In the case of Patrick Brown, including weekends guiding this work to completion. The few remaining details can be handled by the CRA. Those details are actually few, because city staff sweated over those details and worked through all of the stumbling blocks. Congratulations Council members. Tonight you have made history. You have set a mark of success that will benefit the people of Grand Island for generations,” Steele said.

The first item was approving a site redevelopment plan that included requesting $90 million in TIF financing. The project concerns former Nebraska Veterans Home property owned by the City of Grand Island between Webb Road and Broadwell Avenue south of Highway 281/Airport Road.

The second item was approving the first amendment to the Good Life District agreement with Woodsonia GI GLD, LLC. “Under the proposed structure, the city will convey the developer property to the Community Redevelopment Authority (CRA), which will subsequently convey the property to Woodsonia GI GLD, LLC. The amendment establishes a closing deadline of Jan. 29, 2027, and lists a purchase price of $2.75 million. An important provision is that the city will retain all water and irrigation rights associated with the certified irrigated acres located within the property. 

City Administrator Patrick Brown explained at the City Council meeting why the purchase price was lowered from $3 million to $2.75 million. Brown said that the city wanted to retain all water and irrigation rights, which had a value of $5 million. Woodsonia said if it had received those rights, it would have sold the water and irrigation rights. So Brown and Mitch Hohlen, director of development for Woodsonia, agreed to reduce the purchase price to $2.75 million. 

The third item was approving an ordinance authorizing conveyance of city-owned real estate to the Community Redevelopment Authority (CRA), then for conveyance to Woodsonia. The ordinance authorizes the city to convey approximately 335.766 acres of land to the CRA, which would then convey the land to Woodsonia for $2.75 million.

In the first item, developers are anticipating the development will create an additional $421,851,703 of taxable value, Community Development Director Chad Nabity wrote in a memo to the City.

The plan calls for 

*An expanded Veteran’s Sports Complex.

*New housing including 1,500 multi-family units, 200 single-family homes, and middle units consisting of a mix of townhouses, duplexes, and four-plexes.

*Approximately 35 acres of mixed-use ground for future retail services, commercial, office, entertainment, hospitality, and civic uses.

*Eagle Scout Lake expansion/improvements including expansion by 20 acres, dredging to 15-foot depths, over two miles of new walking trails, a public fishing pier, pedestrian bridges, and new landscaping and existing site cleanup.

*Setting aside 11 acres of land for Grand Island Public Schools for a school, probably an elementary school. 

“The developers are anticipating that over the next 60 to 180 months, the development will create an additional $421,851,703 of taxable value and are requesting $90 million in TIF funding. Using the current tax rate of $1.767803 per $100 valuation, this will create an increment of $7,457,507 annually at full development generating an estimated $111,862,606 over 15 years,” Nabity wrote.

“TIF bonds could be in place from 2027 until 2056 with no tax increment debt exceeding a period of 15 years,” Nabity wrote.

The project costs are:

*Veteran’s Village site acquisition costs, $2.75 million (that was lowered from $3 million purchase price listed in Nabity’s memo).

*Total site preparation/infrastructure, $55 million.

*Aquatics center allocation, $22 million.

*Total hard vertical construction costs, $512,085,000.

*Total soft costs, $32,509,675.

Total project costs: $626,344,675 (original total project costs of $626,594,675 minus $250,000 reduction in land purchase price, going from $3 million to $2.75 million).

For the redevelopment plan (source and use of funds), they are:

*Private investment and debt, $387,094,675, 61.78 percent.

*Veteran’s Village occupation tax revenues, $7.5 million, 1.2 percent.

*Veteran’s Village TIF revenues, $90 million, 14.36 percent

*Good Life District proceeds, $142 million, $22.66 percent

Estimated total project cost: $626,594,675.

For the third agenda item, an ordinance was approved authorizing conveying the city-owned real estate to the Community Redevelopment Authority (CRA). 

The ordinance includes protecting the city’s continued use of existing recreational facilities during redevelopment:

*Existing soccer fields: The city would retain a leasehold interest and access to approximately 21.564 acres containing the existing soccer fields. This interest would terminate upon acceptance of new soccer fields in the Good Life District project.

*Eagle Scout Lake: The city would retain a leasehold interest for park purposes on approximately 50.034 acres associated with Eagle Scout Lake.

Jan. 29, 2027, is listed as the deadline for closing. The city would refund the $150,000 earnest money previously deposited by Woodsonia under the earlier transaction structure.

Brown wrote that advantages of using the CRA are:

*”Coordinated redevelopment: Aligns the property conveyance with the CRA’s approved redevelopment plan and associated redevelopment agreement.

*Clear contractual responsibilities: Provides a structure for defining redevelopment obligations, project milestones, and implementation requirements.

*Public accountability: places the redevelopment transaction within the established CRA process, including required public meetings and approvals.

*Protection of city interests: Allows the city to establish conditions regarding compensation, recreational facilities, and retention of water rights.

*Project implementation: Provides a coordinated mechanism for moving the project forward while maintaining consistency with the Good Life District agreement.”

After the City Council meeting was over, Mitch Hohlen, director of development for Woodsonia, commented about next steps in the Good Life District project.

“I think we got through most of the big hurdles tonight. The last one that we need to overcome is the CRA meeting on Friday. That’s where they’ll approve the redevelopment contract. That’s the last large document that needs to be approved. Assuming that’s approved by the CRA on Friday, really all that will be left is the final plat. And then gearing up for closing toward the end of January,” Hohlen said.

“Breaking ground I hope we will start in the March to April timeframe,” he said.

“The first projects Woodsonia will tackle are the site work first, we’ll expand Eagle Scout Lake, we’ll put in all of the infrastructure, then you’ll see the Sports Complex, the YMCA, and the aquatics center coming out of the ground, as soon as site work is completed, which should be in 2028,” Hohlen said.